Pilot
Timing table
October 2004
started activity with nokia 6600
December 2004
start testing with 9500/9300 using Talks first beta and Wea Wecm solutions
January 2005
consolidate hw and sw Environment identified the 7 tester
February 2005
deploy the 7 hw and sw package to users
March 2005
22 March public event in Forum Segrate to announcement
May 2005
public event in Rome for e-gov. Laboratory
May 2005
Closing and reporting pilot experience in a Forum PA event in Rome
September 2005
...
Pilot team
1 Project manager
7 Tester:
- 5 blind people
- 1 low vision people
- 1 normal vision
1 Nokia PM
1 Talks PM
2 other ( lab, Tim, eBOD team,..)